A work center had planned outputs of 10,15,13,and 20 hours with actual outputs of 12,14,13,and 18 hours.What is the cumulative deviation in output?
A) 0
B) 1
C) -1
D) 58
E) Unable to determine with the given information
Correct Answer:
Verified