If job 5 takes 3,4 or 5 hours to be completed by workers A,B,and C,respectively,what would the row values for job 5 be after performing Step 1A of the assignment method?
A) 3,4,5
B) 8,9,10
C) 0,1,2
D) 6,7,8
E) 1,4/3,5/3
Correct Answer: