Multiple Choice
Given an activity's optimistic, most likely, and pessimistic time estimates of 3, 5, and 13 days respectively, compute the expected time for this activity.
A) 3
B) 4
C) 5
D) 6
Correct Answer:
Verified
Related Questions
Q56: Table 11-3 Q57: Table 11-1 Q58: Given an activity's optimistic, most likely, and Q59: Table 11-2 Q60: Table 11-1 Q62: The project described by: Q63: Table 11-4 Unlock this Answer For Free Now! View this answer and more for free by performing one of the following actions Scan the QR code to install the App and get 2 free unlocks Unlock quizzes for free by uploading documents