Consider a project that has an expected completion time of 50 weeks and a standard deviation of 9 weeks.What is the probability that the project is finished in 57 weeks or fewer? (Round to two decimals.)
A) 0.68
B) 0.78
C) 0.22
D) 0.32
Correct Answer:
Verified
Q65: CPM stands for
A)critical path management.
B)critical project management.
C)critical
Q66: The two common techniques for drawing PERT
Q67: Table 11-4
The following represents a project with
Q68: Table 11-4
The following represents a project with
Q69: Your company is considering submitting a bid
Q71: PERT stands for
A)probabilistic evaluation and review technique.
B)program
Q72: Table 11-4
The following represents a project with
Q73: In PERT, we assume that
A)the times to
Q74: Given an activity's optimistic, most likely, and
Q75: The project described by:
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents