Labor Costs in the Project Costs Estimate Are the Estimated

Question 19

Multiple Choice

Labor costs in the project costs estimate are the estimated costs for the various types or classifications of ____ and are based on the estimated work time (not necessarily the same as the activity estimated duration) and the dollar labor rate for each.


A) people who are expected to work on the project
B) people, even if they are not directly assigned to the project
C) overhead and direct expenses
D) subcontractors