Consider a Project That Involves Painting Five Similar Houses Over

Question 45

Multiple Choice

Consider a project that involves painting five similar houses over ten weeks (one house every two weeks) for a total budgeted cost of $20,000.The budget is $4,000 per house.At of the end of week 5, you determine that $10,000 has actually been spent and three houses have been painted completely. What is the earned value of the project?


A) $10,000
B) $12,000
C) $4,000
D) $20,000