The Contractor Might Try to Negotiate Payment Terms That Require

Question 73

Multiple Choice

The contractor might try to negotiate payment terms that require the customer to do one or more of the following except


A) provide frequent payments, such as weekly or monthly payments rather than quarterly payments.
B) make equal monthly payments based on the expected duration of the project.
C) make a single payment at the end of the project.
D) provide a down payment at the start of the project.

Correct Answer:

verifed

Verified