The two-step process for budgeting is
A) estimate the aggregate cost for the activity and distribute the costs over the expected time span.
B) determine the costs and add on contingency amounts.
C) examine past projects that are similar and estimate the amount for the current project.
D) determine the amount of money available from the sponsor and distribute it across the project time required.
Correct Answer:
Verified
Q80: It's crucial that cost variances and inefficiencies
Q81: The to-complete performance index is
A) the amount
Q82: The total budgeted cost for the project
Q83: The key to effective cost control is
Q84: The estimated cost of an activity should
Q86: The earned value is
A) the budgeted cost
Q87: The cumulative earned value of the project
Q88: The cumulative actual costs of a project
Q89: The forecasted cost at completion is
A) a
Q90: The key to managing a cash flow
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents