If an organization or subcontractor has performed similar projects in the past and has kept records of how long specific activities actually took, these historical data
A) can be used as a guide in estimating the durations of similar activities for future projects.
B) have no value for the current project.
C) should be stored in files.
D) should be shared with the customer after the contract is signed to show that the contractor can complete the project.
Correct Answer:
Verified
Q17: The sponsor or customer often states the
Q18: The estimated duration should be aggressive and
Q19: The latest finish time for a specific
Q20: For large projects that involve several hundred
Q21: When the customer requests a change, the
Q23: Changes might be initiated by the customer
Q24: A change in the estimated duration of
Q25: The amount of slack should determine the
Q26: Having the person who will be responsible
Q27: The estimated types and quantities of resources
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents