Negative Slack Indicates a Lack of Slack Over the Entire

Question 79

Multiple Choice

Negative slack indicates a lack of slack over the entire project and the amount of time


A) an activity must be accelerated to complete the project by the required completion time.
B) an activity must be delayed to complete the project by the required completion time.
C) each activity on the critical must be accelerated to complete the project by the required completion time.
D) all activities in the project must be accelerated to complete the project by the required completion time.

Correct Answer:

verifed

Verified