Earliest finish time (EF) is calculated ____.
A) by dividing the activity's latest finish time by the activity's earliest start time.
B) by multiplying the activity's duration estimate with the activity's latest finish time.
C) by adding the activity's duration estimate to the activity's earliest start time.
D) by subtracting the activity's duration estimate from the activity's latest finish time.
Correct Answer:
Verified
Q81: The project control process starts with establishing
Q82: The facilitator for the Scrum development process
Q83: If _ is positive, it represents the
Q84: A regular _ should be established for
Q85: The _ involves regularly gathering data on
Q87: The development team develops, delivers, and demonstrates
Q88: The _ and _ times are determined
Q89: In most cases, eliminating negative slack by
Q90: _ time is the latest time by
Q91: The project team member also referred to
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents