In the network diagram for the following list, what activity immediately follows activity B? Activity
Immediate Predecessor
A
-
B
A
C
A
D
B,C
E
D
F
D
G
E,F
H
G
A) A
B) D
C) C
D) none, B is the starting activity
Correct Answer:
Verified
Q119: A _ shows their appropriate sequence and
Q120: Activities in a network diagram have _,
Q121: In the network diagram for the following
Q122: By participating in the _ of the
Q123: When all the detailed activities have been
Q125: List at least three ways information to
Q126: The _ is a method used to
Q127: A WBS subdivides the project into smaller
Q128: In the network diagram for the following
Q129: Describe the quality standards that must be