Use the data to calculate the schedule performance index for the project for the end of week 20. All amounts are in thousands of dollars.
A) 1.14
B) 0.88
C) 0.94
D) 0.81
Correct Answer:
Verified
Q43: Take the factors considered by earned value
Q44: The earned value to date divided by
Q47: Planned value is:
A)the total budget for the
Q49: A project manager can calculate the projected
Q55: Take the factors considered by earned value
Q56: A project manager can calculate the projected
Q57: Use the data to calculate the schedule
Q58: Use the data to calculate the earned
Q68: The first step in earned value management
Q74: The project baseline is established by combining