Question 24

Multiple Choice

Use the project described in the table to determine the total resources required for activity D if a worker is expected to work half-time (four hours per day) on this project. Use the project described in the table to determine the total resources required for activity D if a worker is expected to work half-time (four hours per day)  on this project.   A)  6 hours B)  40 hours C)  24 hours D)  48 hours


A) 6 hours
B) 40 hours
C) 24 hours
D) 48 hours