Activities A and B have a finish to finish relationship and early start and finish times as shown. What is the result of incorporating a 4 day lag between activities C and B?
A) The early finish for A increases to 31.
B) The early start time for A increases to 24.
C) The early finish time for B increases to 31.
D) The early start time for D falls to 23.
Correct Answer:
Verified
Q18: The primary drawback with _ networks occurs
Q21: Use the Gantt chart and activity list
Q22: Use the Gantt chart and activity list
Q24: Consider the Gantt chart shown below where
Q25: The most common type of logical sequencing
Q26: Use the Gantt chart and activity list
Q28: Activity X has the start to finish
Q33: If a project is extraordinarily complex,rather than
Q38: A finish to start lag delay is
Q65: AOA is a more useful technique than
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents