Work Breakdown Structures typically include one or more intermediate levels.Which of the following statements correctly describe the nature of these intermediate levels?
A) They generally represent items that need to be created in order to create the final deliverables.
B) They generally represent the raw materials required to create the final deliverables.
C) They generally represent the resource assignments to create the final deliverables.
D) They generally represent the sequence and timing of work packages
Correct Answer:
Verified
Q24: The Work Breakdown Structure (WBS)is a framework
Q25: The project scope planning processes include all
Q26: The approved set of procedures that describe
Q27: All of the following conventions are widely
Q28: Which of the following is not a
Q29: Which of the following statements is true
Q30: Once the project is underway,each potential change
Q32: Work Breakdown Structures can be displayed in
Q36: The technique for dividing and subdividing the
Q40: Which of the following statements concerning work
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents