All of the Following Statements Correctly Describe a Contemporary Approach

Question 39

Multiple Choice

All of the following statements correctly describe a contemporary approach to create the Work Breakdown Structure (WBS) for a project EXCEPT:


A) Project teams may adopt a top-down approach to construct the WBS.
B) Project teams may rely upon a WBS from a previous project as a starting point.
C) Project teams may rely upon the project manager to create the entire WBS
D) Project teams may jump start the effort with a brainstorming session.