Which of the following statements concerning work packages is NOT correct?
A) Work packages are the basis for subsequent project planning activities.
B) Work packages are the basis for subsequent project control activities.
C) Work packages are activity elements with detailed descriptions of tasks and dependencies
D) Work packages are the elements at the lowest level of the WBS.
Correct Answer:
Verified
Q34: Define Scope is the process of developing
Q35: Which of the following items best describes
Q36: All of the following elements should be
Q37: Which of the information below would NOT
Q38: A _ is the approved project plan
Q39: It is helpful to list requirements and
Q41: What are some of the benefits of
Q42: Explain how scope is defined on agile
Q43: A typical change request form will include
Q44: Identify and describe the three steps that
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents