Complex projects such as research and development projects often employ rolling wave planning to estimate project costs. Which of the following best describes "rolling wave" planning?
A) Project managers render a definitive estimate for the next stage and an order of magnitude estimate for the remainder of the project.
B) Project managers render an order of magnitude estimate for the next stage and a definitive estimate for the remainder of the project.
C) Project managers render a definitive estimate for all stages of the project during the initiation stage.
D) Project managers render an order of magnitude estimate for all stages of the project
Correct Answer:
Verified
Q10: Typically,expedited costs are preferred over regular costs.
Q22: Which estimating technique uses the cost from
Q23: In addition to optimizing project costs,value engineering
Q26: The documentation of a project cost estimate
Q26: Projects often include indirect costs that are
Q27: There are many causes of variation in
Q29: Which of the following terms best describes
Q34: Costs that repeat as project work continues
Q35: Vendor bid analysis is used to determine
Q38: Which estimating technique decomposes the work into
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents