Figure 14.1 Drug Surveillance Aircraft Project - Monthly Performance Report?(October 31, 20XX)
-Consider the project performance report presented in figure 14.1.What valid conclusion can you draw regarding the project cost performance as of October 31,20XX?
A) The project is $8,000 over budget.
B) The project is $18,000 over budget.
C) The project is on budget.
D) The project is $26,000 under budget.
Correct Answer:
Verified