Concurrent Activities Are

Question 24

Multiple Choice

Concurrent activities are:


A) activities that must be done one after the other.
B) activities that can be performed at the same time.
C) activities that use labor from the same group of workers.
D) activities that use resources from the same resource pool.

Correct Answer: