Use the information in the table to determine the late finish time for Activity B. 
A) day 17
B) day 26
C) day 20
D) day 23
Correct Answer:
Verified
Q65: Use the network diagram and activity lengths
Q66: Use the network diagram and activity lengths
Q67: Use the information in the table to
Q68: What is the float start time for
Q69: What is the slack time for Activity
Q71: Project Test Bank is composed of activities
Q72: Use the information in the table to
Q73: Use the information in the table to
Q74: What is the slack time for activity
Q75: Use the network diagram and activity lengths