Project Test Bank is composed of activities we will refer to as A,B,C,and D for convenience (and lack of creativity) .Durations and precedence requirements are shown in the table.Each of these activities can be conveniently laddered into two sub-activities of equal duration,so activity C in the original project becomes two activities,C1 and C2,each of which lasts 7 days.The first half of each activity serves as the predecessor to its second half and the first half of the original following activity.What is the difference in the late start time for activity C in the original project and activity C1 in the laddered project? 
A) 3
B) 5
C) 7
D) 9
Correct Answer:
Verified
Q59: What is the early start time for
Q60: What is the early finish time for
Q61: Project Test Bank is composed of activities
Q62: Use the network diagram and activity lengths
Q63: Use the network diagram and activity lengths
Q65: Use the network diagram and activity lengths
Q66: Use the network diagram and activity lengths
Q67: Use the information in the table to
Q68: What is the float start time for
Q69: What is the slack time for Activity
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents