Project Terrace has an actual cost of $3,000,but their earned value (all dollar amounts are in hundreds) table appears below.What is their cost variance?
A) $250
B) -$250
C) 1.08
D) 0.92
Correct Answer:
Verified
Q74: The project baseline is established by combining
Q75: Use the earned value table to determine
Q76: The budget variance is calculated as:
A)earned value
Q77: Use the earned value table (all amounts
Q78: In earned value management,schedule variance is defined
Q80: Use the earned value table to determine
Q81: The Project Implementation Profile does NOT contain
Q82: Very short work packages would be better
Q83: Once an activity is begun,it is assumed
Q84: In the formation stage,failed projects are more
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents