Solved

Brierton Company Enters a Contract at the Beginning of Year

Question 18

Multiple Choice

Brierton Company enters a contract at the beginning of year 1 to build a new federal courthouse for a price of $16 million. Brierton estimates that total cost of the project will be $12 million and will take four years to complete.  Costs incurred  Payments from federal government Year 1 $4 million $2 million  Year 2 $4 million $2 million  Year 3 $2 million $6 million  Year 4 $2 million $6 million \begin{array}{lll}&\text { Costs incurred }&\text { Payments from federal}\\&&\text { government}\\\text { Year 1 } & \$ 4 \text { million } & \$ 2 \text { million } \\\text { Year 2 } & \$ 4 \text { million } & \$ 2 \text { million } \\\text { Year 3 } & \$ 2 \text { million } & \$ 6 \text { million } \\\text { Year 4 } & \$ 2 \text { million } & \$ 6 \text { million }\end{array}
-If Brierton used percentage-of-completion method to account for this project, what would they have reported as profit in year 2?


A) $0
B) $1.33 million
C) $1.50 million
D) $0.67 million

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents