In early 2010, the Miami Company signed a contract for construction of an industrial park to be completed in three years.At that time, estimated total costs were $2, 250, 000, and estimated total revenues were $4, 000, 000.During 2010, Miami incurred costs of $960, 000 and collected $1, 100, 000.In December 2010, Miami recalculated total costs for the project to be $3, 200, 000 while estimated total revenues remained unchanged.What amount of profit (loss) should be recognized by Miami for 2010, using the percentage-of-completion method?
A) $266, 667 profit
B) $ 55, 000 loss
C) $240, 000 profit
D) $285, 000 loss
Correct Answer:
Verified
Q27: The percentage-of-completion method does not
A)recognize profit each
Q28: Exhibit 18-1 In 2010, Alpha Construction
Q29: When there is not assurance that the
Q30: Which one of the following types of
Q31: The Key Largo Company uses the percentage-of-completion
Q33: The Naples Company uses the percentage-of-completion method
Q34: An excess of Construction in Progress over
Q35: Exhibit 18-1 In 2010, Alpha Construction
Q36: When merchandise previously sold under an installment
Q37: The deferred gross profit on installment sales
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents