Caterpillar Has Spent $5 Million to Date on a New

Question 50

Multiple Choice

Caterpillar has spent $5 million to date on a new plant,and another $2 million is needed to complete the plant.When construction was started,it was projected that production at the new plant would add $12 million to Cat's profit,but new projections show the additional profit will be only $6 million.Assuming the incomplete plant is worthless,should Cat complete the new plant or abandon it?


A) Cat should complete the plant because it would create a net profit of $4 million.
B) Cat should complete the plant because it would create a net profit of $1 million.
C) Cat should abandon the plant because a $5 million loss is better than a $7 million loss.
D) Cat should abandon the plant because it would create a net loss of $1 million..

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents