A total variance is best defined as the difference between total
A) actual cost and total cost applied for the standard output of the period.
B) standard cost and total cost applied to production.
C) actual cost and total standard cost of the actual input of the period.
D) actual cost and total cost applied for the actual output of the period.
Correct Answer:
Verified
Q81: A company would most likely have an
Q86: The term "standard hours allowed" measures
A)budgeted output
Q87: A large labor efficiency variance is
Q91: Standard costs
A)are estimates of costs attainable only
Q93: A purpose of standard costing is to
A)replace
Q93: The standard predominantly used in Western cultures
Q94: When computing variances from standard costs,the difference
Q94: Which of the following standards can
Q95: An operations flow document
A)tracks the cost and
Q96: Which of the following factors should not
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents