Eight jobs have been sequenced at a single work centre. Total processing time for the eight jobs is 34 hours and total flow time for the sequence is 85 hours. For this schedule, utilization is ________ and average jobs in the system is ________.
A) 100% ; 10.625
B) low; .0941
C) 0.400 or 40%; 2.5
D) 0.235 or 23.5%; 4.25
E) maximized; minimized
Correct Answer:
Verified
Q61: Conventional MRP uses time buckets that do
Q61: Use of the shortest processing time sequencing
Q64: Sequencing (or dispatching)
A) assigns dates to specific
Q66: Which of the following are limitations of
Q67: Average completion time for a schedule sequence
Q69: Which of the following dispatching rules tends
Q69: Which of the following is an advantage
Q70: Five jobs are waiting for processing
Q71: Five jobs are waiting to be
Q75: The most appropriate sequencing rule to use
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents