S contracted to build a machine for F for a price of $8800.00.F paid $1000.00 on account.When the machine was nearly completed,S refused to do more unless F paid another $3000.00.F sued to recover the $1000.00 and for other compensation,and S counterclaimed for the contract price.Expert evidence indicated that the machine was not substantially completed at the time of F's refusal to do more.In this situation at common law
A) F will recover the full $8800.00 even though he defaulted in completing the machine.
B) although the work is not yet completed,a quantum meruit claim can be asserted by S.
C) the contract continues to exist.
D) F's actions together with a failure to complete the machine cancelled the contract,so S will not succeed and must pay back the deposit of $1000.00.
E) none of the above
Correct Answer:
Verified
Q1: A agrees in writing to buy B's
Q2: A and B agree in writing that
Q3: Which of the following provides the best
Q4: While travelling in the U.S.A.,Joey bought some
Q6: A enters into a contract with B
Q7: Park-Lot Maintenance Corp.entered into a three-year contract
Q8: A and B agree in writing that
Q9: A novation agreement respecting a party or
Q10: L contracted with M for the supply
Q11: At common law,in order for a contract
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents