Casey Construction abandoned its $23 million north county road project after spending $7 million. (One progress payment of $5 million had been made.) The county immediately contracted with Beachwood Corp. to take over and finish the project for $21 million. Expectation damages for Casey Construction would be
A) zero, since Casey did $2 million of work where no payment was received.
B) the difference between $18 and $21 million.
C) the difference between $16 and $21 million.
D) the difference between $21 and $23 million.
E) none, only consequential damages might apply.
Correct Answer:
Verified
Q12: Speedy Courier Service had a phrase on
Q13: Mitigation in contract law is best described
Q14: Hastro Toys Mft. operates on a "just-
Q15: Construction of the shopping centre was to
Q16: Houser Inc. (steel fabricators) agreed under contract
Q18: Carlos, an antique dealer, contracted to buy
Q19: Rachel had been looking forward to her
Q20: Working on a firm order, Henry tried
Q21: An order of specific performance
A) requires one
Q22: The purpose of an award of damages
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents