A large disaster cleaning company estimates that 30 percent of the jobs it bids on are finished within the bid time. Looking at a random sample of 8 jobs that it has contracted, calculate the mean number of jobs completed within the bid time.
A) 4.0
B) 2.4
C) 2.0
D) 5.6
Correct Answer:
Verified