In relation to the drum-buffer-rope concept that is used to maximise flow through an organisational bottleneck, the statement that is correct is:
A) the 'buffer' is the activity of only maintaining a small amount of work in process
B) the 'rope' involves calculating the demand for materials according to specified lead times
C) the 'drum' relates to the activity associated with only inserting materials into the constraint when needed
D) All the statements are correct
Correct Answer:
Verified
Q16: In implementing lean accounting concepts the value
Q17: 'Value' in lean accounting is defined through
Q18: Lean accounting refocuses performance measurement systems to
Q19: Physical inspections at every point of the
Q20: Under a total quality management approach entities
Q22: The just-in-time inventory system is considered a:
A)
Q23: The statement concerning the theory of constraints
Q24: Advantages of just-in time inventory management are
Q25: Under TOC a constraint that is a
Q26: Which of these is not associated with
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents