John is a builder engaged by Peter to build his home.The contract states that payment will be made at the end of each stage of construction.On the day of expected completion, John has almost completed construction but the toilets have not been installed.Which of the following is the least likely consequence of John's breach of contract?
A) John is entitled to 95% of the total fee.
B) John is entitled to payment in full less a small adjustment for the failure to install the toilets.
C) John is not entitled to any payment.
D) John is entitled to payment quantum meruit for the work done.
Correct Answer:
Verified
Q47: Jack negotiates with Jill to buy her
Q48: Cyril is a lawyer who wants to
Q49: Jack is a supplier of whiskey.Daniel is
Q50: Which of the following is not a
Q52: Larry visits Zhivago's restaurant.Larry tells Zhivago that
Q54: Mel owns Brazilion Beauty, a beauty salon
Q55: X wants to buy potatoes in bulk
Q55: There is no statutory implied promise by
Q56: X agrees to sell his Porsche to
Q57: Marty and Locke have a contract according
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents