Multiple Choice
What is the early start time for activity C if it has the start to start relationship shown?
A) Day 20
B) Day 25
C) Day 27
D) Day 29
Correct Answer:
Verified
Related Questions
Q1: Activity X has the start to finish
Q2: Activities A and B have a finish