Ray's shipment of materials hit every red light and traffic jam on the way to the site.Upon arrival,half of the material was judged defective,necessitating a trip back to the supplier,and then the same arduous journey back to the site once the new materials were loaded.Traffic was a little better on the second round but the flat tire and subsequent repair caused as much if not more delay than the first trip.In the final analysis:
A) The project activity of Material Delivery was pretty close to the optimistic estimate.
B) The project activity of Material Delivery was pretty close to the most likely estimate.
C) The project activity of Material Delivery had a much higher variance than anticipated.
D) The project activity of Material Delivery was pretty close to the pessimistic estimate.
Correct Answer:
Verified
Q32: An activity has an optimistic time estimate
Q33: Prior to creating a network,it is important
Q34: An activity has an optimistic time estimate
Q35: What are hammock activities and when should
Q36: Consider a project composed of activities X
Q38: Burst activities are those with two or
Q39: A merge activity has two or more
Q40: At a burst point in a backward
Q41: In assigning a value for the most
Q42: What is the late start time
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents