An activity has an optimistic time estimate of 17 days,a most likely estimate of 22 days,and a pessimistic estimate of 32 days.What is the expected duration of the activity?
A) 22.83 days
B) 23.67 days
C) 24.33 days
D) 25.17 days
Correct Answer:
Verified
Q19: Draw a network of any size that
Q20: An activity has an expected duration and
Q21: Preceding activities are those that must occur
Q22: An activity has an optimistic time estimate
Q23: The length of time expected to complete
Q25: Project Test Bank is composed of
Q26: At a merge point in a forward
Q27: Project Test Bank is composed of
Q28: The variance of an activity is given
Q29: An activity has a pessimistic time that
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents