An activity has a pessimistic time that is four times as long as its most likely time and six times as long as its optimistic time.If the activity variance is 12,what is the expected time?
A) About 8 days
B) About 9 days
C) About 10 days
D) About 11 days
Correct Answer:
Verified
Q24: An activity has an optimistic time estimate
Q25: Project Test Bank is composed of
Q26: At a merge point in a forward
Q27: Project Test Bank is composed of
Q28: The variance of an activity is given
Q30: Activity Z has estimates a = 5,b
Q31: What does a network diagram illustrate and
Q32: An activity has an optimistic time estimate
Q33: Prior to creating a network,it is important
Q34: An activity has an optimistic time estimate
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents