A gentleman farmer maniacally works on academic projects to raise funds for his true passion, farming. He has identified seven tasks and developed three time estimates (all in days) of the next big project on the farm, replacing the fence at the comedy pasture. Tasks, precedence requirements, and time estimates are shown in the table. What is the late finish for the Plant Posts activity?
A) 13.3 days
B) 8 days
C) 20.83 days
D) 22 days
Correct Answer:
Verified
Q57: Use the information in the table to
Q58: What is the late start time for
Q59: Use the values in the table to
Q60: Use the information in the table to
Q63: Use the information in the table to
Q64: Compute early and late start and finish
Q65: What is the slack time for Activity
Q67: Phoebe B. Beebee is constructing a canal
Q70: The amount of time an activity may
Q78:
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents