Solved

Which One of the Following Conditions Violates the Assumptions of PERT/CPM

Question 4

Multiple Choice

Which one of the following conditions violates the assumptions of PERT/CPM networks?


A) Two activities tied together by an arc are overlapping and can be worked on simultaneously.
B) Costs increase linearly as activity time is reduced below its normal time.
C) There can be more than one critical path in a network.
D) Some activities can have zero variance.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents