Which one of the following conditions violates the assumptions of PERT/CPM networks?
A) Two activities tied together by an arc are overlapping and can be worked on simultaneously.
B) Costs increase linearly as activity time is reduced below its normal time.
C) There can be more than one critical path in a network.
D) Some activities can have zero variance.
Correct Answer:
Verified
Q1: To calculate the probability of completing a
Q2: Assuming a beta distribution is being used,
Q3: In making an estimate of the most
Q5: Which of the following is NOT one
Q6: When using the beta probability distribution to
Q7: Activity slack is defined as
A) earliest finish
Q8: Which one of the following statements about
Q9: In a network diagram, an "activity"
A) is
Q10: If a project has multiple critical paths,
Q11: Following are four sets of most optimistic,
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents