Table 13.4
Consider the MPS, BOM and inventory data shown below. Master Production Schedule: the following table shows the MPS
start quantities.
Week
Bill of Material
-Item A uses 1 each of component D, 2 each of component C and 2 each of subassembly B.
-Subassembly B uses 1 each of component D.
Selected Inventory Data
Item
-Use the information in Table 13.4. Which one of the following statements concerning item B is TRUE?
A) The first planned order release occurs in week 3.
B) There are exactly 2 planned order releases.
C) The projected on- hand quantity at the end of week 6 is 60 units.
D) There are no action notices needed.
Correct Answer:
Verified
Q45: Table 13.4
Consider the MPS, BOM and
Q46: Which of the following statements about lot-
Q47: Table 13.1. Q48: Use the following MRP record to answer Q49: The Bill of Resources is a list Q51: Which of the following statements regarding the Q52: The lot- sizing rule that generates the Q53: If a planned receipt for an item Q54: A higher than normal level of equipment Q55: Table 13.7.![]()
![]()
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents