Question 56

Multiple Choice

If a project manager notices some slippage on a critical activity, perhaps _____________from a noncritical activity can be borrowed and temporarily assigned to work on the critical one.


A) ideal time
B) process time
C) slack time
D) critical time

Correct Answer: