Solved

The Earliest Start Time (ES) of an Activity

Question 10

Multiple Choice

The earliest start time (ES) of an activity:


A) equals its earliest finish time (EF) minus task time.
B) equals the minimum earliest finish time (EF) of all immediate predecessors.
C) equals the latest start time (LS) for non-critical activities.
D) may not be the same for two or more activities.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents