The earliest start time (ES) of an activity:
A) equals its earliest finish time (EF) minus task time.
B) equals the minimum earliest finish time (EF) of all immediate predecessors.
C) equals the latest start time (LS) for non-critical activities.
D) may not be the same for two or more activities.
Correct Answer:
Verified
Q5: The "forward pass" determines the earliest start
Q6: The earliest start (ES) time for an
Q7: Any attempt at resource leveling always will
Q8: A Gantt chart, by definition, does not
Q9: The critical path shows the earliest project
Q11: A PERT/CPM network can be represented as
Q12: In project scheduling, activities:
A)must be completed sequentially.
B)are
Q13: Typically, the first step in project scheduling
Q14: In PERT, the acceptance of a Beta
Q15: PERT (Program Evaluation and Review Technique) generally
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents