_____ should be used to allocate fixed costs.
A) Actual fraction of capacity used x total budgeted fixed costs
B) Budgeted fraction of capacity available for use x total budgeted fixed costs
C) Actual fraction of capacity used x actual fixed costs
D) Budgeted fraction of capacity available for use x actual fixed costs
Correct Answer:
Verified
Q48: Cost allocation base refers to the _.
A)cost
Q49: The preferred guidelines for allocating service department
Q51: Venice Company has two production departments,
Q52: _ is not a type of cost
Q54: _ should be used to allocate variable
Q55: Joint cost allocations should be ignored for
Q56: Revenues less costs solely associated with by-products
Q57: Type 3 allocations are cost that flow
Q58: The relative-sales-value method requires a common physical
Q128: Joint costs are not allocated to a
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents