Slack equals
A) LF - EF.
B) EF - LF.
C) EF - LS.
D) LF - ES.
Correct Answer:
Verified
Q1: Critical activities are those that can be
Q6: PERT and CPM are applicable only when
Q18: A path through a project network must
Q21: Arcs in a project network indicate
A)completion times.
B)precedence
Q26: Which is not a significant challenge of
Q27: Activities K,M,and S immediately follow activity H,and
Q28: Activities with zero slack
A)can be delayed.
B)must be
Q31: When activity times are uncertain,
A) assume they
Q33: The earliest start time rule
A)compares the starting
Q33: The critical path
A) is any path that