Lear Constructors, Ltd

Question 43

Multiple Choice

Lear Constructors, Ltd.has consistently used the percentage-of-completion method of recognizing income.In 2010, Lear started work on a $7,000,000 construction contract that was completed in 2011.The following information was taken from Lear's 2010 accounting records: Lear Constructors, Ltd.has consistently used the percentage-of-completion method of recognizing income.In 2010, Lear started work on a $7,000,000 construction contract that was completed in 2011.The following information was taken from Lear's 2010 accounting records:   Under the earnings approach, what amount of gross profit should Lear have recognized in 2010 on this contract? A) $700,000. B) $466,667. C) $350,000. D) $233,333. Under the earnings approach, what amount of gross profit should Lear have recognized in 2010 on this contract?


A) $700,000.
B) $466,667.
C) $350,000.
D) $233,333.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents