Slack equals
A) LF - EF.
B) EF - LF.
C) EF - LS.
D) LF - ES.
Correct Answer:
Verified
Q25: Activities following a node
A)can begin as soon
Q26: A critical activity is
A)an activity that consumes
Q27: Activities K,M,and S immediately follow activity H,and
Q28: Activities with zero slack
A)can be delayed.
B)must be
Q29: In deciding which activities to crash,one must
Q31: For an activity with more than one
Q32: Activities G,P,and R are the immediate predecessors
Q33: The earliest start time rule
A)compares the starting
Q34: Which of the following is a general
Q35: Which of the following is NOT a