Which of the following characteristics would make an activity an unattractive candidate for crashing?
A) it is in a bottleneck position
B) it has a long duration
C) employees required to do the job have highly specialized skills
D) it is on the critical path
E) it is labor intensive and employees can be added easily
Correct Answer:
Verified