What is the difference between the critical path and the critical chain?
A) The critical path considers resource availability and the critical chain does not
B) The critical chain considers resource availability and the critical path does not
C) There is no difference - they are exactly the same
D) It is possible to crash activities on the critical path, but activities on the critical chain have already been reduced to their shortest feasible durations.
E) None of the above
Correct Answer:
Verified
Q8: In evaluating time-cost tradeoffs, we start by
Q9: What is the critical chain in the
Q10: The next three questions relate to
Q11: Which of the following is most associated
Q12: When is crashing beneficial to a project?
Q13: Fast tracking is defined as:
A) adding
Q14: The next three questions are related to
Q15: The next three questions relate to
Q16: Research has shown that multitasking has been
Q18: The next three questions are related to
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents