Spencer Inc.applies overhead to production at a predetermined rate of 80% based on direct labor cost.Job No.130, the only job still in process at the end of August, has been charged with manufacturing overhead of $5,000.What was the amount of direct materials charged to Job 130 assuming the balance in Work in Process inventory is $20,000?
A) $5,000.
B) $6,250.
C) $8,750.
D) $20,000.
Correct Answer:
Verified
Q82: The predetermined overhead rate is based on
Q84: The predetermined overhead rate is
A) determined on
Q88: The labor costs that have been identified
Q88: Minton Company provided the following information
Q90: Manufacturing overhead applied is added to direct
Q92: Vektek, Inc.thinks machine hours is the best
Q92: In calculating a predetermined overhead rate a
Q95: Barr Mfg.provided the following information from
Q96: Redman Company manufactures customized desks.The following
Q97: Simmons Inc.applies overhead to production at a
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents